A 66.6% risk is considered as
A. very low
B. low
C. moderate
D. high
The question was asked in a job interview.
My doubt stems from Project Management in division Software Management of Software Engineering
The correct choice is D. high
Easiest explanation: The probability of the risk might be assessed as very low (<10%), low (10–25%), moderate (25–50%), high (50–75%), or very high (>75%).